Deep Main Tile Replacment

The Challenge

Originally installed in 1905, the existing 18-inch concrete tile at the Schultz site had begun collapsing in numerous locations, restricting flow and causing repeated ponding issues.

Location: Southeastern South Dakota

Because the existing line was buried at an extraordinary depth of 19 feet, the project required extensive excavation through heavy clay soils.

The Solution

Water Management Solutions was contracted to design and install a modern replacement system capable of restoring field performance and handling long-term drainage demand.

Because the existing line was buried at an extraordinary depth of 19 feet, the project required extensive excavation through heavy clay soils. Crews utilized multiple CAT excavators, dozers, and GPS-guided trenching systems to safely remove the failed tile and install new dual-wall HDPE mains. Material was screened and reused onsite to ensure stable backfill and final grade integrity.

Material was screened and reused onsite to ensure stable backfill and final grade integrity.

CONCLUSION:

Aerial imagery captured near completion highlights the length and precision of the new system—spanning hundreds of feet of improved main outlet and fully restored surface grade. The upgraded drainage network now provides reliable subsurface flow and improved access across the field, setting the groundwork for higher long-term yield potential.